A
Al Martin
I have a schedule that some tasks required different calendar. For Example A
have a task a duration of 211 days working with the standard calendar 8 Hrs
per day 5 days per week. When I apply the new calendar in this case 20 hrs
per day 6 days per week Project schedule the work correctly; however the
duration still shows 211 days.
I want the duration to show the correct number of days which it would be
about 84.4 days.
In the Microsoft Office Assistance: Understading Calendars in Microsoft
Project 2002, page 4 of 5 tells you "to consider matching the calendar
settings to the working tim on the Calendar tab in the Options dialog box
(Tools menu), when this procedures are followed it fixes the Duration now it
displays 84.4 days, but the duration for the rest of the schedule get
affected too.
Is there any way to match the setting just for one task so it can display
the right duration??
Any help is highly appreciated.
Thank You!
Using Project 2003
have a task a duration of 211 days working with the standard calendar 8 Hrs
per day 5 days per week. When I apply the new calendar in this case 20 hrs
per day 6 days per week Project schedule the work correctly; however the
duration still shows 211 days.
I want the duration to show the correct number of days which it would be
about 84.4 days.
In the Microsoft Office Assistance: Understading Calendars in Microsoft
Project 2002, page 4 of 5 tells you "to consider matching the calendar
settings to the working tim on the Calendar tab in the Options dialog box
(Tools menu), when this procedures are followed it fixes the Duration now it
displays 84.4 days, but the duration for the rest of the schedule get
affected too.
Is there any way to match the setting just for one task so it can display
the right duration??
Any help is highly appreciated.
Thank You!
Using Project 2003