duration

J

Jie

How can I change the task type? I can not change it. for example, I can not change the duration of T1.1
but I can change the task type of Task 1.1.1? Why

Thanks
 
G

Gérard Ducouret

Hello Jie,

The T1.1 task is probably a Summry task with some subtasks ?

Gérard Ducouret

Jie said:
How can I change the task type? I can not change it. for example, I can
not change the duration of T1.1,
 
G

Gérard Ducouret

Jie,

No : the duration of a Summary task is calculated by the software from the
durations of its subordinates, and from the links between them.

Gérard Ducouret
 
M

Mike Glen

The Duration of a Summary task is calculated by Project to be the working
time between the earliest start date and the latest fininsh date of the
subordinate tasks.

Mike Glen
MS Project MVP
 
Top