B
Becca
I would like tasks that use a resource to automatically adjust when changing
the percentage of a persons availability for one of those tasks. For example
Task 1 - uses 50% (of a persons time)
Task 2 - uses 50% (of a persons time)
If I change task 1 to use 70% I would like task 2 to automatically change to
30% in order to avoid overallocations.
Is it also possible to tell tell a task to avoid changing a resources % and
to change another? For example
Task 1 - 30%
Task 2 - 20%
Task 3 - 50%
If I change task 3 to 70% I would like task 1 to change to 10% and avoid
task 2 (all tasks have the same resource and can only have 100%)
the percentage of a persons availability for one of those tasks. For example
Task 1 - uses 50% (of a persons time)
Task 2 - uses 50% (of a persons time)
If I change task 1 to use 70% I would like task 2 to automatically change to
30% in order to avoid overallocations.
Is it also possible to tell tell a task to avoid changing a resources % and
to change another? For example
Task 1 - 30%
Task 2 - 20%
Task 3 - 50%
If I change task 3 to 70% I would like task 1 to change to 10% and avoid
task 2 (all tasks have the same resource and can only have 100%)