Status and % complete of predecessor task

Discussion in 'Project' started by ediofr, Aug 25, 2018.

  1. ediofr

    ediofr

    Joined:
    Aug 25, 2018
    Messages:
    1
    Likes Received:
    0
    Hi, I have a project with several tasks. Some tasks are late because theirs predecessors are late, so the tasks can't start. I need to create 2 fields that show the status and % complete of the predecessor task. For example, the task 54 depends ou task 53. I want 2 fields in line 54 showing the status and % complete of task 53. I think I can't do it using formulas. How can I do it using VBA?
     
    ediofr, Aug 25, 2018
    #1
    1. Advertisements

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments (here). After that, you can post your question and our members will help you out.