K
ken nj
I'm trying to come up with a way to determine which tasks were started
later than they should have been. Early Start is exaclty what I want
because it shows the earliest date that a task could start based on
the predecessors contraints. However, once an Actual Start has been
entered, Early Start takes on that value (can i block this behavior
somehow?). I want to create a report (I am programming asp pages to
run against the sql server db) and i would like to show which tasks
were started late compared to when they could've started. Also, I am
showing which tasks took longer than they should have, ie Actual
Duration more than Base Line Duration. Upper management here wants
to do project post mortems to determine where more resource need to be
focused.
-ken
later than they should have been. Early Start is exaclty what I want
because it shows the earliest date that a task could start based on
the predecessors contraints. However, once an Actual Start has been
entered, Early Start takes on that value (can i block this behavior
somehow?). I want to create a report (I am programming asp pages to
run against the sql server db) and i would like to show which tasks
were started late compared to when they could've started. Also, I am
showing which tasks took longer than they should have, ie Actual
Duration more than Base Line Duration. Upper management here wants
to do project post mortems to determine where more resource need to be
focused.
-ken