P
Pete Smith
Hi,
is it possible configure Project to use the 50/50 Technique for EVA?
Thanks in advance
Pete
is it possible configure Project to use the 50/50 Technique for EVA?
Thanks in advance
Pete
Pete Smith said:Hi,
is it possible configure Project to use the 50/50 Technique for EVA?
Thanks in advance
Pete
John said:Pete,
Sure, it's really a matter of how progress is reported. If value is
"taken" only as 50% and 100% (or other common values such as 25/75.
60/40, etc.), then the EV data will be what you want.
John
Project MVP
davegb said:I think it will work as long as your durations are relatively short. If
you have long duration tasks relative to the duration of your project,
then you will have unreported value being earned, but actual expenses
acruing, throwing off your EV.
Trevor said:The more Tasks that you create, and the shorter their durations, the more
control and accuracy you obtain and the less you need to be concerned about
monitoring and reporting fractions of task completion.
You could settle on "no finer level of progress reporting than 50%
completion" but if you make enough tasks which are indivually short enough
you can happily adopt "no finer level of progress reporting than 100%
completion" without acquiring too much over/under reporting error in a given
period. What doesn't get picked up this month will get picked up next month
(or next week).
See the Tracking Toolbar. It is already set for 0, 25%, 50%, 75%, 100%.
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.