Earned Value Analysis Project 2010

F

Fcoatis

I´m having head aches trying to simulate this in Project 2010
(unsuccessfully):

I have a project to build a new fence. The fence is four sided
(squared). Each side is to take one day to build and is budgeted for
$1,000 per side. The sides are planned to be completed one after the
other. Today is day three.

Using the following project status data calculate PV, EV, AC, BAC, CV,
CPI, SV, SPI, EAC, ETC, VAC.

Side 1: Complete, spent $1,000
Side 2: Complete, spent $1,200
Side 3: 50% done, spent $600
Side 4: Not yet started.

Obviously I made all the calculation manually. But I can´t make
Project 2010 match my results.

Thanks in advance to whoever have the didatic skills to guide me in a
step-by-step tutorial to simulate this in Project 2010.
 
Top