Earned Value by % WORK Complete!

P

Pete Woods

Earned Value in MSP is done by %Complete (useless as its duration dependant
and ignored work done, which is what most people get paid against unless its
level of effort), or physical % complete, which user has to input.
As % work complete exists and is updated by MSP automatically when
statussing, why not allow this to drive the EV method! This would be perfect
for true EV as it would allow EV analysis against work done without the user
needing to copy the values into the Physical % complete column!

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...21102ee&dg=microsoft.public.project.developer
 
Top