Earned Value Calculations

I

Icarus

Hi:
Looking inside columns you can add to MSProject View's I notice that Earned
Value calculations are available, but, When I load the project in VB.Net and
then query these values for each task it always return cero.

Is it posible to automate EV calculation on MSProject? Has already somebody
did it?

TIA
Sergio
 
J

Jack Dahlgren

Have you set a status date and saved a baseline? If not, the values will be
zero.

-Jack Dahlgren
 
R

RobV

You will also need to put rates in for the resources so that the system can
calculate the EV and PV.
 