C
CWW
I am attempting to use Project to calculate EV (BCWP & BCWS) and am
encountering the old catch 22. While progressing tasks, the resources are
applying Actual Work in the future (when ahead of schedule) and the BCWP is
Calculated up to status date. If I move Actual work to before the Status date
and rebasline it corrects the BCWP, However now BCWS is incorrect. Has anyone
encountered the same issue?
encountering the old catch 22. While progressing tasks, the resources are
applying Actual Work in the future (when ahead of schedule) and the BCWP is
Calculated up to status date. If I move Actual work to before the Status date
and rebasline it corrects the BCWP, However now BCWS is incorrect. Has anyone
encountered the same issue?