P
PS
Hello
I have a project with five tasks in it and I ran the earned value report in
Project 2007. In MS Project, I inserted the fields BCWP, BCWS, and ACWP.
When I ran the report, for some reason the EV is equal to the AC and is not
the same value as BCWP in the schedule. I think this might be a bug. Where
does the EV field in the pivot table get its values from? Does it get its
values from BCWP? Can you please explain why the BCWP in the schedule is not
the same as EV in the pivot table?
Thanks.
I have a project with five tasks in it and I ran the earned value report in
Project 2007. In MS Project, I inserted the fields BCWP, BCWS, and ACWP.
When I ran the report, for some reason the EV is equal to the AC and is not
the same value as BCWP in the schedule. I think this might be a bug. Where
does the EV field in the pivot table get its values from? Does it get its
values from BCWP? Can you please explain why the BCWP in the schedule is not
the same as EV in the pivot table?
Thanks.