I just set up my data for Earned Value (using % Complete), loading Standard
Rates, establishing a baseline for the .mpp, scheduled Work hours, and have
team members entering actual hours to My Tasks through Project Server 2007.
However, starting at week 23 in my .mpp, the BCWS is $0.00. Additionally, I
have adjusted the status date from "NA" to a date in the recent past, but
still no BCWS all the way through the .mpp.

Any suggestions?
 
B

Bay

Is it only BCWS that is $0.00, or is it all your Earned Value fields?
Also, have you published everything from Project Pro with all your
updates and accepted all the task updates into your Project Pro
schedule? It sounds like you've double-checked your calculation
settings already...
 