Earned Value Over Time Report in 2007

R

Robert

Hello,

I'm using the Report / Visual Reports feature in Project 2007, but this
feature doesn't export the "Planned Value" (the baseline) beyond the Status
Date. I would like to have this Planned value until the very end of the
project. How can I do that?
Thanks for your help
 
J

JulieS

Hello Robert,

The only way to get the Planned Value (BCWS) to the end of the
project would be to set the Status date to the last day of the
project. However, that will make the other values useless.

Have you considered just adding the Baseline Cost field to the pivot
table?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"Robert" > wrote in message
news:%[email protected]...
 
Top