Greetings,
I'm testing some earned value calculations in MS Project Standard 2003.
I entered tasks, work, assigned resources and baselined the plan.
I then reported progress by entering Actual Work hours using the Resource
Usage view. (I set the status date to the end of the week in which the work
occured).
I then applied the Earned Value table to the Resource Usage View...I see the
earned value fields calculated, specifically BCWP.
However, when I use the Task Usage view on the Earned Value Table, the BCWP
values are still 0 at the Task Level.
Am I missing something?
Any help would be greatly appreciated.
Thanks
Troy
I'm testing some earned value calculations in MS Project Standard 2003.
I entered tasks, work, assigned resources and baselined the plan.
I then reported progress by entering Actual Work hours using the Resource
Usage view. (I set the status date to the end of the week in which the work
occured).
I then applied the Earned Value table to the Resource Usage View...I see the
earned value fields calculated, specifically BCWP.
However, when I use the Task Usage view on the Earned Value Table, the BCWP
values are still 0 at the Task Level.
Am I missing something?
Any help would be greatly appreciated.
Thanks
Troy