W
Wim
I am puzzled on how I need to model correct Earned Value Rptg using
manually entry
(a) actuals hours worked (timephased) and
(b) % complete (of BCWS) in MS Project?
**** Case SetUp ****
Resource A (std cost = 2000 EUR/day)
Task A: Planned Work
= 5days=>PV 10000 EUR
Planned Start Task A: Mon 4/1/2010 (0800)
Planned Finish Task A: Fri 8/1/2010 (1700)
**** Actuals on Fri 8/1/2010 (1700) ****
Res A: Mon 4/1/2010 - 1d
Res A: Tue 5/1/2010 - 1d
% Complete (of BCWS) for Task A: 80%
**** Expected Earned value Figures on Fri 8/1/2010 (1700) ****
BCWS or PV: 10000 EUR
ACWP or AC: 4000 EUR
BCWP or EV: 8000 EUR
**** Problem Description ****
Get correct earned Value reporting using standard MSP functionalities.
**** What is the correct way to enter manually in MS Project both
(a) actuals hours worked and
(b) % complete of the BCWS ? ****
- What (custom) fields/ (custom) views/ (custom) tables need to be used?
- Any specific settings in Tools/Options that require doublechecking?
manually entry
(a) actuals hours worked (timephased) and
(b) % complete (of BCWS) in MS Project?
**** Case SetUp ****
Resource A (std cost = 2000 EUR/day)
Task A: Planned Work
= 5days=>PV 10000 EUR
Planned Start Task A: Mon 4/1/2010 (0800)
Planned Finish Task A: Fri 8/1/2010 (1700)
**** Actuals on Fri 8/1/2010 (1700) ****
Res A: Mon 4/1/2010 - 1d
Res A: Tue 5/1/2010 - 1d
% Complete (of BCWS) for Task A: 80%
**** Expected Earned value Figures on Fri 8/1/2010 (1700) ****
BCWS or PV: 10000 EUR
ACWP or AC: 4000 EUR
BCWP or EV: 8000 EUR
**** Problem Description ****
Get correct earned Value reporting using standard MSP functionalities.
**** What is the correct way to enter manually in MS Project both
(a) actuals hours worked and
(b) % complete of the BCWS ? ****
- What (custom) fields/ (custom) views/ (custom) tables need to be used?
- Any specific settings in Tools/Options that require doublechecking?