K
KingKikapu
Hello.
I work for a large general contractor that has operations throughou
Western Canada. The size of the country makes for somewhat slow receip
of bills/invoices to be inputted into our accounting system (worst cas
it can be up to a month after task completion). I need to track projec
status on a weekly basis. These two facts do not go well together...
We are trying to implement an earned value management system on all o
our major construction projects. The tracking is rigorous and a
objective as I can make it, but I'm experiencing problems when we try t
import our actual costs from our accounting software for complete
tasks.
Since the actual costs reported in our accounting software migh
trickle in over the span of a few weeks, if I import the actual costs
have on file into some sort of actual cost field in project before al
of the bills are received in our accounting software, then my CPI's wil
be grossly over optimistic, thereby messing up all predictions for EA
(at which point why bother even doing EVM)
Somebody must have come up against this before. For a 100% complet
task: is there some sort of other field that I can place my actuals i
that won't overwrite the full baseline cost for a task, thereby keepin
CPI realistic? The only thing I can think of to plug the hole is t
also input the matching open purchase orders in as the remaining costs.
That way there should be some semblance of balance.
What does everyone think
I work for a large general contractor that has operations throughou
Western Canada. The size of the country makes for somewhat slow receip
of bills/invoices to be inputted into our accounting system (worst cas
it can be up to a month after task completion). I need to track projec
status on a weekly basis. These two facts do not go well together...
We are trying to implement an earned value management system on all o
our major construction projects. The tracking is rigorous and a
objective as I can make it, but I'm experiencing problems when we try t
import our actual costs from our accounting software for complete
tasks.
Since the actual costs reported in our accounting software migh
trickle in over the span of a few weeks, if I import the actual costs
have on file into some sort of actual cost field in project before al
of the bills are received in our accounting software, then my CPI's wil
be grossly over optimistic, thereby messing up all predictions for EA
(at which point why bother even doing EVM)
Somebody must have come up against this before. For a 100% complet
task: is there some sort of other field that I can place my actuals i
that won't overwrite the full baseline cost for a task, thereby keepin
CPI realistic? The only thing I can think of to plug the hole is t
also input the matching open purchase orders in as the remaining costs.
That way there should be some semblance of balance.
What does everyone think