Earned Value Report

C

ChelseaWarren

I am a brand new user and need to create an Earned Value Report for a class.
I've entered planned resources and costs, saved a baseline, changed
percentage of completion for some tasks and entered actual costs. The
variance amount shows in the cost table but when I try to display an Earned
Value Report all I get are zeros. (I also did a manual calculation on the
project.)

What am I doing wrong?

Thank you so much for any help.
 
P

Pratta

Hi Chelsea
Looks like you have done most things to get a reading.
Try the following.
-Make sure that a resource has a cost rate per day.
-Baseline all tasks using Tools/Tracking/Save baseline
-Select a task and complete it in total or in part.
-Insert columns for BCWP and ACWP, they should both have values.
-If so as CPI = BCWP/ACWP then it must have a value
-Insert a column for CPI, it MUST have a value in it

Of either are zero, then CPI will be zero

Best Regards
 
S

Steve House

Be sure to set the Status Date field in the Project Information dialog box
(Project menu) to your desired reporting date.
 
C

ChelseaWarren

Steve and Pratta:

Thank you both so much for your replies. I wound up doing all those things
late last night (early this AM) and was able to make it work. The last thing
I did was change the status date and it solved the problem.

Thanks again.

Steve House said:
Be sure to set the Status Date field in the Project Information dialog box
(Project menu) to your desired reporting date.

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


ChelseaWarren said:
I am a brand new user and need to create an Earned Value Report for a
class.
I've entered planned resources and costs, saved a baseline, changed
percentage of completion for some tasks and entered actual costs. The
variance amount shows in the cost table but when I try to display an
Earned
Value Report all I get are zeros. (I also did a manual calculation on the
project.)

What am I doing wrong?

Thank you so much for any help.
 
H

Hung

What was the old value of your Status date, NA or an old date?
Will it be computed correctly if we clear Status date to NA?

ChelseaWarren said:
Steve and Pratta:

Thank you both so much for your replies. I wound up doing all those things
late last night (early this AM) and was able to make it work. The last thing
I did was change the status date and it solved the problem.

Thanks again.

Steve House said:
Be sure to set the Status Date field in the Project Information dialog box
(Project menu) to your desired reporting date.

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


ChelseaWarren said:
I am a brand new user and need to create an Earned Value Report for a
class.
I've entered planned resources and costs, saved a baseline, changed
percentage of completion for some tasks and entered actual costs. The
variance amount shows in the cost table but when I try to display an
Earned
Value Report all I get are zeros. (I also did a manual calculation on the
project.)

What am I doing wrong?

Thank you so much for any help.
 