Cost Loaded Schedule and Earned Value Report

B

bsky201

I have a cost loaded report and am running an earned value report to provide
to my customer as backup for an invoice. I have one task that is not
calculating correctly on the EV report. My task is 75% complete with a total
cost value of $95,264.18. The Actual Cost column in the "Cost" view is
correctly showing $71,448.14 but the earned value report is showing
$19,052.84 in the ACWP column (which is 20% of the value). All other tasks
are calculating correctly. Why is this happeniong and how can it be
corrected?
 
J

JulieS

Hi Bsky201,

Do you have a cost resource assigned to the task? Resources of cost
type are not included in EV calculations.

Try a google groups search on this newsgroup for "Cost resources
earned value 2007" and you'll see quite a discussion about this
issue.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top