I have a cost loaded report and am running an earned value report to provide
to my customer as backup for an invoice. I have one task that is not
calculating correctly on the EV report. My task is 75% complete with a total
cost value of $95,264.18. The Actual Cost column in the "Cost" view is
correctly showing $71,448.14 but the earned value report is showing
$19,052.84 in the ACWP column (which is 20% of the value). All other tasks
are calculating correctly. Why is this happeniong and how can it be
corrected?