N
New Earned Value
I am new to Earned Value and am trying to determine how to apply it to my
project. I have a 38,000 hour project which runs for 1 year. When I created
my MS Project plan, I entered my tasks and placed dependencies on the tasks
purely based on the fixed number of resources that I have. So, person A
would work task 1, then task 2, then task 3. Person B would work task 4,
then task 5, then task 6. That approach set start/end dates for the task.
In reality, person A does a little bit of task 1, task 2, task 3, then goes
back to do some more on task 1, task 2, task 3. When I try to apply Earned
Value, it doesn't seem to work correctly. For my first week, I only had 40
hours of work that was scheduled to be completed. It was all for task 1.
However, when I entered my actuals which showed that 40.25 hours of work were
completed against task 1-3, my earned value seems to calculate weirdly.
My BCWS was 40 (which seems right to me), my ACWP was 40.25 (which also
seems right based on my actuals), but the BCWP was 124.02.
First, I don't understand how the BCWP was calculated.
Second, what would be the best way of applying earned value analysis to this
type of project?
project. I have a 38,000 hour project which runs for 1 year. When I created
my MS Project plan, I entered my tasks and placed dependencies on the tasks
purely based on the fixed number of resources that I have. So, person A
would work task 1, then task 2, then task 3. Person B would work task 4,
then task 5, then task 6. That approach set start/end dates for the task.
In reality, person A does a little bit of task 1, task 2, task 3, then goes
back to do some more on task 1, task 2, task 3. When I try to apply Earned
Value, it doesn't seem to work correctly. For my first week, I only had 40
hours of work that was scheduled to be completed. It was all for task 1.
However, when I entered my actuals which showed that 40.25 hours of work were
completed against task 1-3, my earned value seems to calculate weirdly.
My BCWS was 40 (which seems right to me), my ACWP was 40.25 (which also
seems right based on my actuals), but the BCWP was 124.02.
First, I don't understand how the BCWP was calculated.
Second, what would be the best way of applying earned value analysis to this
type of project?