J
Jan M.
Hi,
I made a very simple project in order to understand how MS Project is
calculating earned value:
1 task
Work: 8h
Duration: 1 day
Resource: 1 person at 100%
STD rate: 1$ per h
I applied the task usage view and entered 4 hours of real work on the first
day. Then I modified the remaining work a couple of times to see the effect
on BCWP. What I found out was quite surprising:
BCWP of the assignment was different than BCWP of the task! I didn't
expected this since there is only one resource assigned to the task.
Shouldn't the assignment and the task show the same BCWP in this situation?
Can anybody explain?
Thanks
Jan M.
I made a very simple project in order to understand how MS Project is
calculating earned value:
1 task
Work: 8h
Duration: 1 day
Resource: 1 person at 100%
STD rate: 1$ per h
I applied the task usage view and entered 4 hours of real work on the first
day. Then I modified the remaining work a couple of times to see the effect
on BCWP. What I found out was quite surprising:
BCWP of the assignment was different than BCWP of the task! I didn't
expected this since there is only one resource assigned to the task.
Shouldn't the assignment and the task show the same BCWP in this situation?
Can anybody explain?
Thanks
Jan M.