Hello
I running a Earned value analyze based on phisical % complete and cost and
have got calculated BCWP-values on the project based on my status at 30.01.08.
Is it possible to distribute the remaining cost(Baseline cost - BCWP) on the
activities from status date to the end of the activities?
Helge Svee
I running a Earned value analyze based on phisical % complete and cost and
have got calculated BCWP-values on the project based on my status at 30.01.08.
Is it possible to distribute the remaining cost(Baseline cost - BCWP) on the
activities from status date to the end of the activities?