Edit fields in timesheet view

M

miriam.zidek

I have the following problem:

I'm using published fields and a modified timesheet view in the tasks
section of PWA. The additional fields (editable) ar shown in the left
pane of the timesheet view next to the regulary fields of the tasks.

Is there a possibility to have published fields in the right side pane
of this view?

Resources report there actually work done per day and I would like to
have them reporting also a description of there work done per day,
that means an additional field per day.

Can anyone help me?

thanks,
Miriam
 
D

Dale Howard

Miriam --

Sorry to give you bad news, but you cannot add extra fields (rows) to the
timesheet as you wish. The only rows of information visible there for each
task assignment are:

Actual Work
Scheduled Work
Actual Overtime Work

The best you can do is to add extra published fields to the left side of the
View My Tasks page (the task list), and to ask your people to add Notes to
each task as they complete their work. Hope this helps.
 