S
Steve Scott
I have a list of 12 x forecast costs for each month in 2006. I want to have
a split view with Task usage at the top and Gantt View at the bottom. I want
to be able to Manually enter the costs per month (not allow project to spread
it automatically from just one total) and then be able to drag the Gantt bars
back and forth and see the costs month back and foward accordingly. Is this
at all possible? It works with Work but not costs.
a split view with Task usage at the top and Gantt View at the bottom. I want
to be able to Manually enter the costs per month (not allow project to spread
it automatically from just one total) and then be able to drag the Gantt bars
back and forth and see the costs month back and foward accordingly. Is this
at all possible? It works with Work but not costs.