Edit My task views? server 2k2

A

Armin

Hello all,

I have looked, but not been able to figure out how, or
find how-tos to edit the columns and orders of the View My
tasks under the Tasks tab.

The manage views under admin does allow me to edit other
views (though not as well as I would have hoped) but I
have zero access over view my tasks. any thoughts?

Does any one also know if server 2k3 allows more
customization?
 
D

Dale Howard [MVP]

Armin --

In Project Server 2002, the Project Server administrator cannot modify the
default timesheet view for users on the View My Tasks page. Team members
are allowed to "drag and drop" the columns in any order they wish, however.
In Project Server 2003, the administrator can modify the default Timesheet
view and show only the columns the organization needs. Hope this helps.
 