L
lynne baker
Hi
We're running project server 2002 and project pro 2002 and PWA
Further to the issue of tasks finishing earlier than anticipated, we
now have the problem that the dates of successor tasks move forward,
which we don't want.
Ideally we would like the successor tasks to stay where they are, and
for the free time to be allocated elsewhere.
We are tracking the fact that tasks have finished earlier by entering
100% and remaining hours to 0.
Is there a way to prevent successor task dates from moving forward?
The problem is that it makes resource issues elsewhere!
Any help is greatly appreciated
Many thanks
lynne
We're running project server 2002 and project pro 2002 and PWA
Further to the issue of tasks finishing earlier than anticipated, we
now have the problem that the dates of successor tasks move forward,
which we don't want.
Ideally we would like the successor tasks to stay where they are, and
for the free time to be allocated elsewhere.
We are tracking the fact that tasks have finished earlier by entering
100% and remaining hours to 0.
Is there a way to prevent successor task dates from moving forward?
The problem is that it makes resource issues elsewhere!
Any help is greatly appreciated
Many thanks
lynne