Effort capture

S

Sriram

Hi,

Is it possible to enable both % complete and Actual Work
fields to be editable in Porject Web Access for Team
Members to enter ?

Regards

Sriram
 
S

Sriram

Dale :

I have choosen Option 1 : Percent of work complete but it
only allows % Work Complete and Remaining Work. We need %
Work Complete and Actual Work to be updatable or is it
possible to capture Actual Overtime Work WITHOUT affecting
the schedule BUT overallocation the resource for a task ?

Please let know your comments.

Regards

Sriram
 
D

Dale Howard

Sriram --

You can't mix two modes of tracking progress in a single project. If you
use the % Work Complete method, your resources can only enter values in the
% Work Complete and Remaining Work fields. When the user enters the % Work
Complete value, PWA automatically calculates their Actual Work and Remaining
Work values. If the user adjusts that Remaining Work value, the % Work
Complete will be recalculated.

If you really need your team members to enter their Actual Work and Actual
Overtime Work, then you will need to change your method of tracking progress
to the Actual Work and Remaining Work method. And please note this, any
method of tracking progress that you select WILL affect the schedule, since
that is what the software is programmed to do. Hope this followup helps.

--
Dale A. Howard
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
Top