effort details for a project for each resource on daily granularit

S

Suman Sarkar

For a given project, effort details need to be reported for each resource on
a daily granularity for a given period. Currently, the resource report
(view->reports->workload->task usage) shows time reported for a given
resource across all projects at a weekly granularity. This does not suffice
the need. Can you please help me in getting the report I want.

Suman
 
W

Willy_comp

Susan,

When you use "Resource Usage view" and define a new group with the following
items :
a) Group by "Project"
check "group assignments, not resources"
select "assignment" as Field type
B) then by "Name"
with field type "resources"

You get an overview per project per resource

regards,
Willy V
 
Top