Effort Driven and Estimations ?

S

Sameer

is there a way where i can specify that all the new tasks created by ANY PM's
will not be effort driven.

I need to set it globally rather then on a single PM's local machine.

Any sort of help will be appreciated.

Thnx in advance.
Regards
Sameer Khan
 
G

Gary L. Chefetz [MVP]

Sameer:

Set this in your Enterprise template(s) and direct your managers to use one
of them to create all new projects.
 