KK said:
John can dig. John can drive the truck. John cannot operate the crane.
Pete can dig. Pete cannot drive the truck. Pete can operate the crane.
I would like to define the above resources in Project 2000 so that for
"Drive the truck" I use John. For "Operate the crane" I use Pete. But for
"Dig" I can use Joh or Pete and project selects them automatically dependent
on who is free, without me having to determine who is free.
Can I do that?
KK,
Man that John, (or is it Joh), is one versatile guy. I hire him in a
flash.....unless of course I need a crane.
The solution is simple. Assign the right resources to the right task.
But you are going to have to do it. How can Project possibly know who
has what talents? If it did, then that meant that you provided the
information to Project. So, why not just "tell" Project by making the
right assignments.
In order for it not to sound as if I'm jumping on you and then pounding
you to a pulp for not being the project manger, here is what Project
2000 can do (later versions do expand the resource function a bit but
nowhere near what you are asking). Let's say you have a group of
painters. Some of them are a little faster, some are a little neater and
some are more precise, but basically any one of them could do your
painting tasks. On the Resource Sheet, create a resource set called
"painters". Set the Max units to be consistent with however many
painters you have. For example, one painter is 100% and 5 painters are
500%. Now, for all your painting tasks simply assign the resource
"painters" at the appropriate level. For example if you need one and a
half painters for a given task assign the painters at 150%.
A resource set allows the project manger to set up functional resources
without having to identify specific resources by name. It can be very
useful when you may not know, or care, who does the work but you do know
you don't want to overallocate the resources you do have.
Hope this helps.
John
Project MVP