lilyliu16
I have a resource has assignement as the follows
Task 1-> 3rd Dec - 7th Dec, 100%, Work=5d
Task 2-> 10th Dec-14th Dec, 100%, Work = 5d.
Since this resource will not be working on task 2, I zeroed out the
remaining work of 5d for task 2 and hence Work also becomes 0d as
there's no Acutal yet. I've also put 0% for unit in task information,
Resoruce tab. For the Physical completion and % completion column, I
put 100%.
All changes published and re-ran the cube. Now, through PWA ->
Resources->view resource assignment. the end date for this particular
resource is still 14th Dec rather than 7th Dec.
What do I need to do so that it picks up the updated end date as Work
has been zeroed out for that resources.
Many thanks in advance.
Task 1-> 3rd Dec - 7th Dec, 100%, Work=5d
Task 2-> 10th Dec-14th Dec, 100%, Work = 5d.
Since this resource will not be working on task 2, I zeroed out the
remaining work of 5d for task 2 and hence Work also becomes 0d as
there's no Acutal yet. I've also put 0% for unit in task information,
Resoruce tab. For the Physical completion and % completion column, I
put 100%.
All changes published and re-ran the cube. Now, through PWA ->
Resources->view resource assignment. the end date for this particular
resource is still 14th Dec rather than 7th Dec.
What do I need to do so that it picks up the updated end date as Work
has been zeroed out for that resources.
Many thanks in advance.