Entering Actual Time into Timesheets

S

Spencer

I am unable to enter actual time into the timesheets view
of tasks. Users are able to add percentages but not
actual hours.

Using Project 2003 Server in Enterprise running on
Windows 2003 Enterprise Server running Project 2003.

Any assistance would be appreciated
 
D

Dale Howard [MVP]

Spencer --

You will need to do the following to rectify this situation:

1. Ask your Project Server administrator to change the default method of
tracking projects within your system to Actual Hours Worked Per Day or Per
Week
2. Ask each of your project managers to open and republish the assignments
in every one of their projects using Collaborate - Publish - Republish
Assignments

Hope this helps.
 