E
Earl Forrence
Hi everyone,
Simple question ...
Just getting to production with MS-P Enterprise -- 2002
(long time in works). My need is to have Task Assignees
be able to enter their time in the Tasks / Timesheet View
(Web Access) ... not just % Work Complete and Remaining
Time which is on the Left-Hand side of the display.
So,
... while I have found where I can get Act. Work to
display in the Timesheet view on the Right Hand side, and
... while I can see from Project Inside Out where Act.
Work should be enterable there,
... I unfortunately can not find where I can make them
available for entry.
Any help appreciated ... thanks ... Earl
Simple question ...
Just getting to production with MS-P Enterprise -- 2002
(long time in works). My need is to have Task Assignees
be able to enter their time in the Tasks / Timesheet View
(Web Access) ... not just % Work Complete and Remaining
Time which is on the Left-Hand side of the display.
So,
... while I have found where I can get Act. Work to
display in the Timesheet view on the Right Hand side, and
... while I can see from Project Inside Out where Act.
Work should be enterable there,
... I unfortunately can not find where I can make them
available for entry.
Any help appreciated ... thanks ... Earl