Entering Day by Day Comments on Tasks via PWA?

R

rolfb

Hi,
I'm facing a problem with PWA and Project Server 2003
We need to be able to enter comments for tasks on a daily basis via PWA.
These comments are needed for invoicing and include a brief summary of the
work executed for the day.
Is there a way to do this without customization?
Are there tools around which plug into PWA?
Does 2007 offer this kind of functionality?

Any idea is more than welcome!

Rolf
 
P

Paul Conroy

In 2007 you can amend task notes in PWA. I can't remember if this was
available in 2003 !
 
A

ahelp

2003 PWA also has a Notes feature. With the desired task selected, click on
the "Insert Notes" button on the toolbar. When the team member updates & the
PM accepts, the notes will be available in Project. Double click on the Notes
icon in the indicator field--either in PWA or Project.
 