Entering Overtime Work in PWA?

R

Rajan

Hello,

How or where do I enter Overtime work in Project Web Access?

I would highly appreciate for the earliest reply/solution.

Thanks in Advance.

Rajan
 
D

Dale Howard [MVP]

Rajan --

Navigate to the View my tasks page, click the View Options tab, and select
the "Show overtime work" tab. Hope this helps.
 
R

Rajan

Dale,

I had already tried that, but the field 'Overtime Work' is read-only. What
should I do to make it editable for resources in PWA?

Rajan
 
D

Dale Howard [MVP]

Rajan --

If you are using either the % Work Complete or Actual Work Done and Work
Remaining method of tracking, then you cannot track actual overtime work on
the View My Tasks page in PWA. Sorry.
 
Top