S
sender
I am new to project, and have a basic question.
Is there a way to enter time for a task as hours and not as a percent
complete.
for example, a task is 16 hrs. and the assigned person does 4 hrsof work on
it. is there a way to enter 4 hrs and not 25 percent?
thanks in advance
Is there a way to enter time for a task as hours and not as a percent
complete.
for example, a task is 16 hrs. and the assigned person does 4 hrsof work on
it. is there a way to enter 4 hrs and not 25 percent?
thanks in advance