I wondered if there is any way to enter time for a task whose start date has
not yet arrived? We frequently have folks who work on tasks in advance of
the actual scheduled start date and it is a bit of a problem for us. Thanks
for your help.

Debbie
 
D

Dale Howard [MVP]

Debbie --

You can certainly enter time against future tasks in PWA. This is known as
"out of sequence progress" and it is allowable under one condition: the
progress must be entered in the current reporting period. This will cause
the task to start early, which by the way is what really did happen. Hope
this helps.
 
D

dt @ dsc

Thanks Dale that will help me.

Debbie

Dale Howard said:
Debbie --

You can certainly enter time against future tasks in PWA. This is known as
"out of sequence progress" and it is allowable under one condition: the
progress must be entered in the current reporting period. This will cause
the task to start early, which by the way is what really did happen. Hope
this helps.
 