How can i create an enterprise calendar for my Project server 2003, also how
can i specify public holidays on new projects and also for previously
published projects?

Thank you
 
D

Dale Howard [MVP]

Batayneh --

Do the following:

1. Launch Microsoft Project Professional and log into Project Server with
administrator permissions
2. Click Tools - Enterprise Options - Open Enterprise Global
3. Click Tools - Change Working Time
4. Set all of your company holidays as nonworking time on the Standard
calendar
5. Click OK
6. Save and close the Enterprise Global
7. Close and relaunch Microsoft Project Professional

All projects that use the Standard calendar as the Project Calendar will
automatically rececive your company holidays the next time their project
manager launches Microsoft Project Professional, logs into Project Server,
and opens a project. Hope this helps.
 
B

Batayneh

Howard,

That was very helpfull, Thanks Alot.

Dale Howard said:
Batayneh --

Do the following:

1. Launch Microsoft Project Professional and log into Project Server with
administrator permissions
2. Click Tools - Enterprise Options - Open Enterprise Global
3. Click Tools - Change Working Time
4. Set all of your company holidays as nonworking time on the Standard
calendar
5. Click OK
6. Save and close the Enterprise Global
7. Close and relaunch Microsoft Project Professional

All projects that use the Standard calendar as the Project Calendar will
automatically rececive your company holidays the next time their project
manager launches Microsoft Project Professional, logs into Project Server,
and opens a project. Hope this helps.
 