Enterprise Calendars switching projects to use a different one

A

Alice Roman

Hi,
I have an enterprise calendar which is not the standard one. How can
I get our projects to use that as the default?
I've tried within the project by going into Tools, change working
time, selecting the calendar, ok, but it always defaults back to the
standard calendar.
 
D

Dale Howard [MVP]

Alice --

Set the new custom calendar as the Project Calendar and the Nonworking Time
Calendar in each enterprise project template your organization uses. Beyond
this, you CANNOT change the default calendar selected for new blank projects
on each user's PC, as it always defaults to the Standard calendar. Hope
this helps.
 