P
ProjectAnalyst
We have used a 7 hour per day calendar to reflect that resources don't
actually work 8 hours on a project.
We'd like to refine that to having an 8 hour per day calendar and more
carefully assign and manage the resources.
My thoughts are:
1. Simply take the existing calendar and add an hour to each day.
2. Create a new calendar with 8 hours per day and assign all resources and
new projects to it.
Anybody have any warnings or better ideas? Thanks.
actually work 8 hours on a project.
We'd like to refine that to having an 8 hour per day calendar and more
carefully assign and manage the resources.
My thoughts are:
1. Simply take the existing calendar and add an hour to each day.
2. Create a new calendar with 8 hours per day and assign all resources and
new projects to it.
Anybody have any warnings or better ideas? Thanks.