Hello all,

We are deploying EPM 2007 and we created all kind of enterprise custom
fields. Required and non required fields but we only see the Required fields
in Project Information in Microsoft Project.

Does anyone know how we could see the non required fields in the Project
Information?

Thanks in advice!!!

Regards,

Manfred
 
D

Dale Howard [MVP]

Manfred --

The Project Information dialog contains only required and optional custom
enterprise Project fields. You cannot see custom enterprise Task or
Resource fields in that dialog. Are you saying you have optional Project
fields that are not showing up there? Let us know.
 
M

Manfred

Dale,

Thanks for your answer!!!

We tried the field state with a lookup table the show in the project
information field but we didn't see it in the project information. We made an
other field and that works. So we used another field.

Regards,

Manfred
 
D

Dale Howard [MVP]

Manfred --

The State field is used only with Proposals and not with projects, which is
why you do not see the State field in the Project Information dialog. In
spite of this, you found a workaround that solved your problem. Way to go!
:)

Hope this helps.
 