Enterprise Fields on Project Server 2007 and Visual Basic

U

Uriy

As in Visual Basic it is possible to read out data from enterprise fields
created on Project Server
 
R

Rod Gill

In Project Server 2007 look at the _User Views in the Reporting database.
There is one for Projects, Tasks, Resources and Assignments.

In Project Server 2003 read the pjsrvr.htm file and it tells you how. I
recommend reading the MSP_VIEW tables.

In VBA 2003 simply use the field name, EG
activeproject.Tasks(1).EnterpriseCost1

In 2007 it's a little more complex, use:
GetField(FieldNameToFieldConstant("Custom Field Name"))

--

Rod Gill
Project MVP

NEW!! Project VBA Book, for details visit: http://www.projectvbabook.com
 