Enterprise & Project Reporting: Resource Utilization

N

Ned Shamon

Hi.
Similar to the issue related to deleting an Enterprise
Project (Valerie, 11/18 10:26AM); the software manual and
my Microsoft-published book, PROJECT 2002 INSIDE OUT
appear to have almost no specifics on how to utilize
Project 2k2 Server Portfolio Analyzer. Is there anyplace
I can find this information online?
More specifically, I would like to build reports around
the following parameters: Enterprise Resources'
utilization (both individual resources and specified
Resource Groups) BY projects or tasks within projects BY
time period. As you may know, the resource reports that
available within a the MSProj 2k2 client software have not
changed since MSProj 98 and are very limited.
Thank you!
Ned
 
K

Kevin Flanagan

Once your OLAP cube is built, you go to the Admin section
of PWA and to Manage Views and saet up a Portfolio
Analyzer view there. You will need to have the Office XP
Web Components installed on your machine. Basically it
is just like working with a pivot table in Excdel where
you choose your fields and the relationships you want.

Kevin
 
N

Ned Shamon

Thanks very much Dale.

Have you (or anyone) ever been able to report resource
allocation by tasks within a project--as opposed to
allocation among projects?
 