K
Karrybelle
My PMs don't like to use resource leveling and enterprise resources because
the enterprise resources are always "over allocated" and when the PMs add
them to their project plans it causes the plan to push out dates for the
tasks and changes the end date. So then my PMs end up creating local
resources or end up changing the resources avalible units to a lot more than
just 100% and we lose the ability to use Resource Center or analyze resources
in the Portfolio Analyzer.
Is there any way to allow a enterprise resource to be over allocated without
having to adjust the units avalible or adding a secondary resource so the end
dates do not change? We don't have always have another resource avalible
because some of the resources are our only SMEs.
Hopefully I explained my question well enough and if not I can reword it if
requested.
Thanks for your help!
the enterprise resources are always "over allocated" and when the PMs add
them to their project plans it causes the plan to push out dates for the
tasks and changes the end date. So then my PMs end up creating local
resources or end up changing the resources avalible units to a lot more than
just 100% and we lose the ability to use Resource Center or analyze resources
in the Portfolio Analyzer.
Is there any way to allow a enterprise resource to be over allocated without
having to adjust the units avalible or adding a secondary resource so the end
dates do not change? We don't have always have another resource avalible
because some of the resources are our only SMEs.
Hopefully I explained my question well enough and if not I can reword it if
requested.
Thanks for your help!