NW --
When you select a project in the Project Center and then click the Edit
button, the Project Details page displays all custom enterprise Project
outline
codes currently in use, plus only those enterprise Project fields that do
not contain either a value list or a formula. By chance, does your
Entperprise Project Text1 field contain a value list? And do your
Enterprise Project Number fields contain formulas?
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"