N
Nicky Ang
I have an enterprise resource "ABC" that works 4 hours for Project A in the
morning and another 4 hours for Project B in the afternoon, everday. This
goes on from 1-Jan to 31-Jan.
On enterprise level, ABC's "max. units" is set to 100%, standard calendar, 8
hours a day.
In MS Project, I would like to book "ABC" from 1-Jan to 31-Jan in both
project A and B. Meaning 50% is for Proj A and 50% for Proj B.
What is the correct way to enter such planning in MS Project?