J
John
I have a handful of enterprise resources assigned to tasks on a project. I
have no problems with the performance and functionality up to that point.
However, now I want to add fields that are local to this project only, but
that store data about a resource (hence, the data that I want to store about
the resource is not going to be stored globally about all enterprise
resources). The problem I am having is this: if I create a new local field
in my resource view, then edit the field for my first resource, I get a
message telling me that my changes to the enterprise resource will be lost.
I don't want to modify the data on a global scale, but don't know how to add
data at the individual project level about enterprise resources.
Any help you can give me would be appreciated.
Thanks
John
have no problems with the performance and functionality up to that point.
However, now I want to add fields that are local to this project only, but
that store data about a resource (hence, the data that I want to store about
the resource is not going to be stored globally about all enterprise
resources). The problem I am having is this: if I create a new local field
in my resource view, then edit the field for my first resource, I get a
message telling me that my changes to the enterprise resource will be lost.
I don't want to modify the data on a global scale, but don't know how to add
data at the individual project level about enterprise resources.
Any help you can give me would be appreciated.
Thanks
John