Enterprise resources with different calendars on different projects

P

Paul Galushin

My resources used on several projects. And projects use different calendars.
Can I assign resource on different projects to different calendars? Thank
you.

Pavel
IT manager
 
D

Dale Howard [MVP]

Pavel --

Each enterprise resource an have only a single Base Calendar, which
determines the working and nonworking schedule for that resource. When you
assign a resource to a task in a project which has a Project calendar
different from the resource's Base Calendar, Microsoft Project schedules the
work on the task assignment according to the resource's schedule on the
resource's Base Calendar. If you wish to override the working schedule on
that task to conform to the schedule on the Project calendar, you must
double-click the task, select the Advanced tab, select the Project calendar
as the task Calendar, and then select the "Scheduling ignores resource
calendars" option. If everyone working on the project must work the
schedule dictated by the Project calendar, then click the select all button
to select every task, click the Task Information button on the Standard
toolbar, and complete the previous steps to apply a task calendar to every
task in the project. Hope this helps.
 
P

Paul Galushin

Thanks for you help, Dale!
It really helps!


Dale Howard said:
Pavel --

Each enterprise resource an have only a single Base Calendar, which
determines the working and nonworking schedule for that resource. When you
assign a resource to a task in a project which has a Project calendar
different from the resource's Base Calendar, Microsoft Project schedules the
work on the task assignment according to the resource's schedule on the
resource's Base Calendar. If you wish to override the working schedule on
that task to conform to the schedule on the Project calendar, you must
double-click the task, select the Advanced tab, select the Project calendar
as the task Calendar, and then select the "Scheduling ignores resource
calendars" option. If everyone working on the project must work the
schedule dictated by the Project calendar, then click the select all button
to select every task, click the Task Information button on the Standard
toolbar, and complete the previous steps to apply a task calendar to every
task in the project. Hope this helps.
 