Hi Keith,
You said you created the resource into the enterprise resources...
however after that's done you have to associate/add a resource to a project
for you to assign them to a task... there are many different ways to do
this... MY prefered method is this...
Click on the task you want to add someone to.
Click Assign Resources Button.
Open up the Resource list options.
Click Add Resources.
Select From Project Server...
Now if you created your resource accounts correctly they should appear on
the left half of your screen. Highlight the ones you want and click the
"Add >" button. You can now assign them to a task and it will appear in
their PWA (project web access) timesheet. If they are NOT in that area then
you created them as users of PWA and did NOT create them as PWA resource.
If this is the case e-mail me at
[email protected] and I'll provide
further assistance.
Hope this was helpful!
-Brian Stebbins