Enterprise task and project fields - seeing ETC01 in Project Centre

  • Thread starter Richard Greenall
  • Start date
R

Richard Greenall

I have used EntTaskCost01 field to identify certain costs
in a project pertaining to certain tasks only. Works well
in Project View (I get roll-up of ETC01 field showing a
sub-set of project costs)

I'm now trying to show this value in a Project Centre
view, so I have the rolled-up total seen in the Project
Centre.

Having trouble with referencing the EntTaskCost01 for
Project Centre view. I've tried:
1. adding in cost1 field
2. using a formula where EPC01=ETC01, and also =Sum(ETC01)

Neither works - must be missing siomething... Can someone
assist?

Thanks Richard.
 