I am trying to get the enterprisetasktext1 field to show up in timesheets.
I have followed the instructions on projectserverexperts.com
(http://www.projectserverexperts.com/Project Server FAQs/changetimesheet
..htm) and I logged in as the admin and managed the timesheet view and added
my custom field. I am still having the following problems:
The field DOES show up in timesheets view, BUT there is no data in the
field.
I have three projects published right now. I reopened all of them and
republished the assignments and made sure that I had my data in the
enterprisetasktext1 field. For each project, I went to
Tools-Customize-Published Fields and made sure that enterprisetasktext1 was
selected to be published. I also opened the enterprise global template and
did the same for Published Fields.
Am I missing something? How can I get the data in my enterprisetasktext1
field to show up on timesheets? Thanks.
I have followed the instructions on projectserverexperts.com
(http://www.projectserverexperts.com/Project Server FAQs/changetimesheet
..htm) and I logged in as the admin and managed the timesheet view and added
my custom field. I am still having the following problems:
The field DOES show up in timesheets view, BUT there is no data in the
field.
I have three projects published right now. I reopened all of them and
republished the assignments and made sure that I had my data in the
enterprisetasktext1 field. For each project, I went to
Tools-Customize-Published Fields and made sure that enterprisetasktext1 was
selected to be published. I also opened the enterprise global template and
did the same for Published Fields.
Am I missing something? How can I get the data in my enterprisetasktext1
field to show up on timesheets? Thanks.