EnterpriseTaskText1 Field in Timesheets

R

RockNRoll

I am trying to get the enterprisetasktext1 field to show up in timesheets.
I have followed the instructions on projectserverexperts.com
(http://www.projectserverexperts.com/Project Server FAQs/changetimesheet
..htm) and I logged in as the admin and managed the timesheet view and added
my custom field. I am still having the following problems:

The field DOES show up in timesheets view, BUT there is no data in the
field.

I have three projects published right now. I reopened all of them and
republished the assignments and made sure that I had my data in the
enterprisetasktext1 field. For each project, I went to
Tools-Customize-Published Fields and made sure that enterprisetasktext1 was
selected to be published. I also opened the enterprise global template and
did the same for Published Fields.

Am I missing something? How can I get the data in my enterprisetasktext1
field to show up on timesheets? Thanks.
 
D

David Gage (MVP)

I have actually seen a similar issue on the Assignments View with
custom enterprise task fields in Project Server 2003. It is possible
that this is a bug but I don't know yet. I turned it over to Microsoft
Support.

David
 